How to Split a Task on a Timesheet (Customize the LOV) | Learn with Rego 

Nov 23, 2016 09:40 AM

Dear Community Members,

 

In today's Q&A, we have the instructions for how to split a task on a timesheet and several other topics.

 

We also have two webinars coming up. Join us for a Resource Management BrightTALK with LabCorp. They'll share the IT approach we helped them develop in CA PPM that powerfully improved Resource Management and their ability to respond to business needs. The event is live on December 1st @ 1:00PM EST. Sign up by clicking the link above.

 

And if you're interested in Agile and how to scale Agile, join us December 6th @ 12:00PM EST. This webinar includes the story of a major retailer who successfully made the transition.

 

And now for our Q&A!

 

Q&A Summary

 

1. How do you setup financials for Non-Labor resources? 

 

2. Does Allocation on NPIO update ETC?

 

3. Can we split a task on a timesheet? Customize the LOV? 

 

4. Why are Assignments resetting to 0% in MSP? 

 

5. Why isn't a simple Process sending emails?

 

Please feel free to comment on any alternative answers you've found.

 

We love your input (always).

 

 

1.

How do you setup financials for Non-Labor resources? Do they require a Department and Location, when they're not owned by any department?

Answer

 

The Department and Location fields are required to process financial transactions, since it's how the non-labor resources are tied to the entity. We recommend selecting the top-most department or a default department.

 

2.

Does allocation on NPIO auto-generate ETC? 

Answer

 

The allocation on NPIOs has created matching ETC for some time, perhaps since v8 and the introduction of NPIOs. You may not have noticed before because the automatic Effort Task that gets generated for NPIOs is hidden in the UI. You don't see the Tasks tab on them, but all resources staffed to an NPIO get assigned to the effort task with ETCs.

 

 

3.

Can we split a task on a timesheet? Customize one of the OOTB LOV fields? We'd like to allow Developers to specify the actual application on which they're working. As an example, I book my time to the "Development" task of a project established to create a new business capability. This capability will be used by a number of applications. Based on the work I'm doing that week, I actually select the application right on my timesheet...splitting the task as necessary if multiple records are required.

 Answer

 

Absolutely. We've attached a TEC guide below that details options for implementing a dynamic lookup within the financially-enabled User Value lookup on a timesheet. The file is named: "TEC545084-How can we use our own user-defined lookup with the Time Entry User Value 1 field.docx."

 

4.

Why are Assignments resetting to 0% in MSP? 
·        We open a project schedule in MS Project (e.g. PROJ00010103).
·        All assignments look normal with different percentages of units after the resource names.
·        I added a resource to a task at 10%, and 
·        Saved the schedule back to Clarity. Received the saved successfully message.
·        Downloaded the schedule again to MSP.
·        All units of all assignments have been reset to 0%.
Answer
Check the settings in CA PPM Admin > Project Management > Settings. You want to make sure the “Task Assignment %” maps correctly and doesn’t get reset to the “Default Allocation %” for the resource on the Project Team Page in MSP. See the screenshot below.

 

Also set the Default Load Pattern to “Uniform” from “Front,” otherwise your distribution of hours will not be correct in MSP.

 

 


 

5.

Why isn't a simple process sending emails? This is a custom gel process that sends out a notification when new projects are created. The process message states that the process runs fine, but we're not receiving emails. 
Answer 

Try checking off ‘Use Authentication’ in the NSA > Properties > System page. This particular system had a dummy user niku with password niku.

 

THANK YOU------------------------------  

A special thanks to Daniel GreerJohn Fechenbach, Dave Wachsmann, Atul Kunkulol, Mindy Calderon, Wes McCoubrie, Lisa Olsen, Ramesh Rathnam, Ram Iyer, Sankhadeep Dhar, Derrick Tetlow, Navdeep Joshi, Jenn Rinellaand the Rego Team for this Q/A material.

TRAINING------------------------------   

Webinar | MEISTERPLAN Resource Planning: From Pain to Gain. Presented by Scott McLaughlin from Citrix and Stephan Anders from itdesign with Rego Consulting.

 

 

Half-day classes in Jaspersoft or Portfolio Management are Free and Limited.

 

 

Report Valued @ $500. Free Here: Agility is now a prerequisite for successful firms and enterprise architecture professionals . . .  

 

JOIN US------------------------------  

BrightTALK | How LabCorp Improved Resource Management with CA PPM December 1, 2016 @ 1:00PM EST

For healthcare companies, managing priorities, projects and resources can be a critical factor in getting to market faster, improving patient outcomes and even saving lives. For LabCorp, working with Rego Consulting to develop an innovative new approach to IT Resource Management—using CA PPM—has powerfully improved their IT Organization’s ability to respond to business needs in delivering solutions. Join LabCorp’s Paul Soper, along with Rob Greca from Rego Consulting and Walter Angus from CA Technologies, to learn how LabCorp utilized data they were already collecting to develop IT labor capacity and supply/demand balancing without creating new business processes. 

  

Webinar | Scale Agile to Run with Waterfall

December 6, 2016 @ 12:00PM EST

Best practices for managing, scaling, and running Agile alongside Waterfall. Hear about how a major retailer successfully made the transition.

 

regoUniversity 2017 at La Cantera Resort & Spa -

San Antonio, TX: April 23-27, 2017. 

Hands-on CA PPM Training with over one hundred companies who use the tool daily.

Click here for Early Bird Pricing.

Statistics
0 Favorited
0 Views
1 Files
0 Shares
2 Downloads
Attachment(s)
docx file
TEC545084-How can we use our own user-defined lookup with....docx   592 KB   1 version
Uploaded - May 29, 2019

Related Entries and Links

No Related Resource entered.