Hi,
There is 1 specific environment where all project (task) in OWB -> Gantt bars are shown in GREY no matter what the task status is.
According to OWB color settings, grey indicates "task lock for scheduling? -> yes".
I've used same OWB to open projects from other environments.. and I don't have that issue.
Not sure why OWB thinks tasks are locked. I made sure:
++ sercurity.logs is empty
++ tables empty: PRJ_tentative_projects and PRJ_tentative_tasks
++ Task is not Lock in Clarity UI before launching it..
Not sure what else needs to be checked. Any idea?