We have hours tracked to ongoing Business as Usual project that should be tracked under an Investment project. Has anyone come up with a good way to move tasks and hours from one project to another without going through the pain of adjusting timesheets?
If you are in a post v12 version that is not possible other than adjustment timesheets or XOGing those.
Third party integration/data migration/transfer tools might also do that.
Check these -
TEC562321 - Explain WIP Reversal and WIP Transfer actions.docx
Transfer of Actuals / Transactions
https://communities.ca.com/message/46112356