  • 1.  How to edit child project task details from parent project

    Posted Sep 19, 2016 05:42 AM

    when we create a sub project the parent project will have the dummy task of child task in parent task's list.

    can we edit that data from parent project?

    can we add resources to that task or remove resources from child task from parent project?



  • 2.  Re: How to edit child project task details from parent project

    Posted Sep 19, 2016 05:47 AM

    If this is a CA PPM question please post it in the CA PPM community questions.



  • 3.  Re: How to edit child project task details from parent project

    Posted Sep 19, 2016 05:52 AM

    Thank you urmas



  • 4.  Re: How to edit child project task details from parent project

    Posted Sep 19, 2016 09:53 AM


  • 5.  Re: How to edit child project task details from parent project

    Posted Sep 20, 2016 05:57 AM

    Can any one help me in solving the problem........!!



  • 6.  Re: How to edit child project task details from parent project

    Posted Sep 20, 2016 06:51 AM

    When you open the master project in OWB in edit mode, the child project would also be loaded (if I recall correctly ) You can then, edit the tasks of the sub-project

     

    NJ