when we create a sub project the parent project will have the dummy task of child task in parent task's list.
can we edit that data from parent project?
can we add resources to that task or remove resources from child task from parent project?
If this is a CA PPM question please post it in the CA PPM community questions.
Thank you urmas
This is the same as this:
How to edit child project task details from parent project
NJ
Can any one help me in solving the problem........!!
When you open the master project in OWB in edit mode, the child project would also be loaded (if I recall correctly ) You can then, edit the tasks of the sub-project