    Hi

    We've got a number of Projects where the finish date of a task has been pushed out to the end of 2017 (29/12/17). The resource allocated to the task are allocated to the end of 2017 and have ETC.

     

    When the resource books time in Nov 16 to the task and we run the Post Timesheet job the finish date of the task is being changed to the latest date of the booked time e.g. 11/11/16. This is happening on a number of Projects but not on most of them.

     

    Does anyone have any idea why this is happening? I'd expect it to move the finish date out if the time booked was later than the finish date on the task but not the other way round.


    Thanks

    Richard



  • 2.  Re: Task finish date being updated when Post Timesheet Job runs

    Posted Nov 18, 2016 10:07 AM

    Check this:

     

    Task start and finish date changes after posting timesheets

    Task start and finish date changes after posting timesheets  

     

    NJ



  • 3.  Re: Task finish date being updated when Post Timesheet Job runs

    Posted Nov 18, 2016 11:15 AM

    Thanks NJ, that's useful information but not sure if this answers my problem. The resource is assigned to the end of 2017 and has ETC so I wouldn't expect the finish date of the task to be changed when time is booked to the task



  • 4.  Re: Task finish date being updated when Post Timesheet Job runs

    Posted Jan 09, 2017 05:57 PM

    Hi 

     

    I'd suggest to log a ticket with CA Support.