Clarity

  • 1.  Monthly Availability in PRJ_BLB_SLICES

    Posted Mar 23, 2017 05:50 AM

    A resource start date is July-2016 and end date is July 2018.

    its availability in prj_blb_slices with respect to slice request id=7 is only up to july 2017. 

    while in prj_blb_slices_m_avl resource availability is there up to July 2018.

     

    Slice details in prj_blb_slicerequest table for monthly availability slice:

    Request_Name=MONTHLYRESOURCEAVAILCURVE

    From_Date = 16-03-01

    No of Period=60

    Expiration Date= 17-04-01

    Request_completed_date=17-03-23

    to_date= 21-03-01

     

    Please help to understand why this resource availability is not getting reflected in PRJ_BLB_SLICES table properly



  • 2.  Re: Monthly Availability in PRJ_BLB_SLICES

    Broadcom Employee
    Posted Mar 23, 2017 07:41 AM

    Hi Prachi

    You meant to go to the PPM not APM group. Saw this in passing. Moving. Please in the future place in teh correct Community else you will not get a timely answer

     

    Thanks

    Hal German

     

    Resource Planning: Allocations Monthly Detail 



  • 3.  Re: Monthly Availability in PRJ_BLB_SLICES

    Posted Mar 23, 2017 08:40 AM

    Thanks Hallett. I will take care of this in future.



  • 4.  Re: Monthly Availability in PRJ_BLB_SLICES

    Broadcom Employee
    Posted Mar 23, 2017 12:06 PM

    The monthly slice #7 is a roll up of the daily slice #1.

    Check the Datamart Entity MONTHLY Fiscal Time periods are configured to go beyond July and are activated.

    Then run the Datamart Extraction job.

     

    Also, reference the following article:

    How Should I Configure My Time Slices?