A resource start date is July-2016 and end date is July 2018.
its availability in prj_blb_slices with respect to slice request id=7 is only up to july 2017.
while in prj_blb_slices_m_avl resource availability is there up to July 2018.
Slice details in prj_blb_slicerequest table for monthly availability slice:
Request_Name=MONTHLYRESOURCEAVAILCURVE
From_Date = 16-03-01
No of Period=60
Expiration Date= 17-04-01
Request_completed_date=17-03-23
to_date= 21-03-01
Please help to understand why this resource availability is not getting reflected in PRJ_BLB_SLICES table properly