Hi Vit_Posel,
The sequence of the jobs are all good. Can you please check the following
1. Please check the Posted Transaction Review portlet and see if the transactions for this project - resource - task is showing up in the portlet.
2. When you enter timesheet and run post timesheet, the ACWP is updated but the Cost Plan pulls data from the WIP tables. This means, the timesheet should flow all the way to WIP to show up in the cost plan. If you dont see the records in #1, it means the transactions are stuck somewhere like - prtimeentry.prrmexported = 0 or invalid transactions or waiting for post to wip. I do see that you have done Post to WIP but please check the filters applied.
If you see the transactions in the posted transaction review portlet, please share a screenshot of that too.
Also please let us know the CA PPM version you are on.
Thanks,
Jerin