How do I include both units (hours) and costs as default settings for the creation and edit of cost plans? I've tried to add the Total Units, Actual Units and Variance Units to the cost plan views but it's not working. We want to be able to capture both approved costs and approved hours for our projects. Help is appreciated. Thanks!
Hi Randi,
Like elsewhere in studio, you generally need to publish the changes for this to feed through to ALL users.
If the user has configured the cost plan in any way, then your changes wouldn't show. You'd need them to reset to default or force a publish.
I've seen a few occasions in multi server clusters where config hasn't applied, a restart of the services normally fixes that.
If you want to know who is impacted, get in touch and i'll share the query
Andrew