Hi Anthony,
No we dont have that but here are some pre requisites and high level steps
Pre Requisites
1. Ensure PPM version along with patch is same for production and development
High Level steps
1. Take a database dump/export from production while services are stopped as we have seen issues with Hot back up
2. Stop all the PPM services on Development
3. Start the CSA and Beacon service and update the database details
4. If all the connections are successful then you can start the app and bg services
Note: As you said you dont have development now then below steps you should follow
1. Install a Vanila PPM on one of the box with the database dump provided with the ISO
2. Upgrade to the patch level of current production by applying the patch
3. Once the patch is successful stop all the services and import the production database dump to development database and you should be good to go
Let me know if you run into any issues.
Regards
Suman Pramanik