2 resources were removed from Time entry in Team level, but still they have posted time on that project.
What could be the scenarios ?
The scenario could be that the timeentries were created and approved prior to removing the time entry in team level.
Are the resources still open for CA PPM timeentry?
Are the tasks open for timeentry?
Task is open for Time entry but all the resources are removed from Time entry in that project.
When were the timeentries created before or after removing the timeentry in that project?
Do the resources have the right to add unassigned tasks and is that project property true or false?
I think the open for timeentry is checked when the entry is created. After that any changes do not have effect.
^ yep ; here are some previous discussions;
Timebooking to tasks closed after timesheet population
Closed to Time Entry Tasks on In-Flight Timesheets
(legacy UI related, I would assume the new UI follows the same logic though)