  • 1.  Staff->Properties page Change % allocation to hours

    Posted Feb 15, 2019 11:35 AM

    CA PPM 15.5

     

    On the Project->Team->Staff Properties, is there anyway to update the % allocation to hours for each segment?

     

    In the New UX, we have FTE and Hours but in the classic view, we would like to use hours instead of Percent

     

    The system attribute datatype is percent and is it possible to use custom attribute on this page?

     



  • 2.  Re: Staff->Properties page Change % allocation to hours
    Best Answer

    Broadcom Employee
    Posted Feb 15, 2019 12:08 PM

    Hello,

     

    This seems to be the same as asked on this post:

    Resource Allocation - Planned Allocation - % to Days 

     

    Check that out and see if that helps.

     

    Cheers,

    Raúl



  • 3.  Re: Staff->Properties page Change % allocation to hours

    Posted Feb 15, 2019 12:11 PM

    Thanks Raul but the link is referring to the portlet but I'm looking at the staff->properties page Planned Allocation and Hard Allocation Segments by period.



  • 4.  Re: Staff->Properties page Change % allocation to hours

    Posted Feb 15, 2019 01:00 PM

    My recollection is that you can't display hours, but have to use another view or portlet to see the hours.



  • 5.  Re: Staff->Properties page Change % allocation to hours

    Broadcom Employee
    Posted Feb 15, 2019 01:11 PM

    I see.

    That section on the Staff Member Properties page does not appear to be configurable.

    Object: Team - Views (Staff Member Properties)

     

    I see an old idea asking for the allocation to be also displayed in hours

    https://communities.ca.com/ideas/103026943 

     

    See if that one helps:

    Staff member properties Planned Allocations 

     

    Cheers,

    Raúl