Question with regard to Part Time calculation:
I have a resource who works 4 days a week:
The resource is set with availability of 7.5 hours a day.
The resource calendar is populated 4 days, with Wednesday off.
The resource shift patterns are set as below.
3 days = 7.5 hours (Monday, Tuesday, Friday)
1 day = 8 hours (Thursday)
Available Hours:
Based on the resource availability = 4 days x 7.5 = 30 hours per week
Based on the resource shift pattern = 3 days x 7.5 + 1 day x 8 = 30.50 hours per week
The base calendar is set as 5 days a week at 7.5 hours a day = 37.50 hours per week
When I ask for a resource for each day the resulting allocation is as follows:
| Monday | Tuesday | Wednesday | Thursday | Friday |
---|
Hours | 7.03 | 7.03 | 0 | 7.5 | 7.03 |
Days | 0.94 | 0.94 | 0 | 1 | 0.94 |
FTE | 0.04 | 0.04 | 0 | 0.05 | 0.04 |
Please confirm WHY?
I was expecting to see Monday, Tuesday, Friday with 7.5 hours and Thursday with 8 hours.
Where has the 7.03 come from?
Please help - this is REALLY REALLY CONFUSING!!
Many Thanks,
Karen.