As per Clarity PPM Glossary, I found the below information. When I checked few resources, the Remaining allocation is incorrect. Ex: Allocation is 503.85 - Actuals are 309 and the Remaining allocation should be 195 but the system is showing 72.28. Unable to figure out what is causing the difference. Any pointer is greatly appreciated.
remaining allocation
The remaining allocation is the effort remaining on the project shown in the effort unit of measure such as Hours or FTE.
Remaining Allocation = Allocation - Actuals