AnsweredAssumed Answered

Timesheet Population Logic for Other Work

Question asked by hue_nguyen on Jan 16, 2013
Latest reply on Mar 21, 2013 by navzjoshi00
Hi everybody

I got a little bit confuse about the timesheet population for Other Work.

As i understand, below is timesheet population logic for Task

1.
If the resource is assigned to any tasks and the duration of which falls under current timesheet period, then it will appear on timesheet once clicked on populate button.
2.
If the task is not put to completed status and task duration falls under current timesheet period, even though the resource assignment for the task is finished, it will be populated once clicked on populate button.

But this logic doesnt work for Other work since when I click on Populate button, the other work items are getting populated randomly.

Could anyone share me how exactly the populate button works?

Best regards,
Hue Nguyen