Average % Allocation in Project

Question asked by hue_nguyen on Jan 16, 2013
Latest reply on Jan 17, 2013 by another_martink
Hi everyone

I got a case as below

My resource is assigned into a project and her average %allocation is differrent from default allocation. For normal case, if a resource is assigned into the project just only one time period, her average %allocation should be same with assigned %allocation. But in this case, my resource is assigned (30%) to project from the in one time period but her average allocation (28.5%)
(From project\team page. i saw her allocation into project is 28.5%
I checked her allocation properties i saw that Default Allocation :30%, i checked if she was assigned in some different durations but i just saw only one long duration (from project start to close date) and allocation for that is 30%.)


As i understand, Average %allocation is the avarage of allocation that that resources was assigned into that project.
For example
Project duration 01 Jan 2013 to 31 Dec 2013
A is assigned 30% allocation from 01 Jan to 30 Jun2013 and is assigned 60% from 01Jul 2013 to 31 Dec 2013.

=> A's average %allocation will be ~45% in the project.

Please kindly advise.
Hue Nguyen