Mark as completed task without actuals

Question asked by juancardila on Feb 6, 2013
Latest reply on Feb 7, 2013 by navzjoshi00
Hello,

We have several projects with the % Complete Calculation Method setup to Effort, because we need that the tasks, activities, and phases, update their % Complete automatically based on their estimated effort and actuals. However, we have some tasks that have no one assigned because they are sub contractors or third parties who are responsible for them. The problem we are having is that we still haven't found how to mark as completed these tasks, which don't have estimates and actuals.

When a task is marked as Milestone it allows changing the status to completed, which is what we are looking for, but we just don't want to fill our projects with a ton of unreal milestones.

We are using version 12.0.5

Appreciate your help.

Juan