Unload resource allocation info to msproject from Clarity

Question asked by Khairon on Mar 18, 2013
Latest reply on Mar 22, 2013 by another_martink
Dear Experts,

I have the following specific question to solve.

For example I have 1 resource that have been allocated to several projects.

When planing project schedule in MS Project (with schedule connect to Clarity) - is it possible to see detailed resource utilization over all projects that rosource have been assigned via MS Project interface. To be able to schedule resource on tasks correctly.

If that is not, then share experience how to schedule project with no info about current detailed resource assigments on other projects on per day basis (for example) regarding to Clarity best practices.

Hope for your reply,
Best Regards,
Sergey