  • 1.  Timesheet - Task cannot be added into timesheet

    Posted Mar 29, 2013 08:12 AM
    For one project we lost possibility to add task into timesheet.

    Team members can timesheet against this project/task in past (so they have actuals)

    Project settings :
    open for time entry = true
    track mode = Clarity.

    Team members are assigned to task and have ETC.

    My technical colleague check database and they are in assignments table for this task and project.

    Task duration is from 2.1.2013 to 31.5.2013

    Any suggestion?

    Thank you in advance
    Vit


  • 2.  RE: Timesheet - Task cannot be added into timesheet
    Best Answer

    Posted Mar 29, 2013 08:16 AM
    apologies if you already verified this, but is the resource iteself open for time entry at the project level, and is the task iteslf (including any parent phases) open for time entry?


  • 3.  RE: Timesheet - Task cannot be added into timesheet

    Posted Mar 29, 2013 08:21 AM
    Thank you Scott:
    one parent task in hiearchy was not open for time entry.
    Now its OK.
    Thank you for quick and usefull help.


  • 4.  RE: Timesheet - Task cannot be added into timesheet

    Posted Mar 29, 2013 08:34 AM
    Just to close in the loop, below is the query which runs at the backend when adding task to timesheet -

    SELECT * FROM ( SELECT T.PRID AS TASK_ID
    ,T.PRNAME AS NAME
    ,T.PREXTERNALID AS UNIQUE_NAME
    ,T.PRSTART AS START_DATE
    ,T.PRFINISH AS FINISH_DATE
    ,T.PRSTATUS AS TASK_STATUS
    ,T.PRWBSSEQUENCE
    ,P.ID AS PROJECT_ID
    ,P.NAME AS PROJECT_NAME
    ,P.CODE AS PROJECT_UNIQUE_NAME
    FROM INV_INVESTMENTS P, INV_PROJECTS PRJ, PRTEAM
    , PRTASK T , (SELECT prtaskid, prresourceid FROM PRASSIGNMENT WHERE PRRESOURCEID=<ResourceID>) A
    WHERE T.PRID = A.PRTASKID AND PRTEAM.PRRESOURCEID=<ResourceID>
    AND PRTEAM.PRISOPEN <> 0
    AND P.ID = PRTEAM.PRPROJECTID
    AND P.IS_ACTIVE <> 0
    AND PRJ.PRID = P.ID AND PRJ.IS_TEMPLATE = 0
    AND P.IS_OPEN_FOR_TE <> 0 AND P.TRACK_MODE = 2
    AND T.PRPROJECTID = P.ID
    AND T.PRISMILESTONE = 0
    AND T.PRISTASK <> 0
    AND T.IS_OPEN_TE = 1 AND T.PRSTATUS <> 2 MINUS
    SELECT T.PRID AS TASK_ID
    ,T.PRNAME AS NAME
    ,T.PREXTERNALID AS UNIQUE_NAME
    ,T.PRSTART AS START_DATE
    ,T.PRFINISH AS FINISH_DATE
    ,T.PRSTATUS AS TASK_STATUS
    ,T.PRWBSSEQUENCE
    ,P.ID AS PROJECT_ID
    ,P.NAME AS PROJECT_NAME
    ,P.CODE AS PROJECT_UNIQUE_NAME
    FROM INV_INVESTMENTS P, INV_PROJECTS PRJ, PRTEAM
    , PRTASK T , (SELECT prtaskid, prresourceid FROM PRASSIGNMENT WHERE PRRESOURCEID=<ResourceID>) A
    WHERE T.PRID = A.PRTASKID AND PRTEAM.PRRESOURCEID=<ResourceID>
    AND PRTEAM.PRISOPEN <> 0
    AND P.ID = PRTEAM.PRPROJECTID
    AND P.IS_ACTIVE <> 0
    AND PRJ.PRID = P.ID AND PRJ.IS_TEMPLATE = 0
    AND P.IS_OPEN_FOR_TE <> 0 AND P.TRACK_MODE = 2
    AND T.PRPROJECTID = P.ID
    AND T.PRISMILESTONE = 0
    AND T.PRISTASK <> 0
    AND T.IS_OPEN_TE = 1
    AND (EXISTS
    (SELECT PARENT.PRID FROM PRTASK PARENT
    WHERE PARENT.PRPROJECTID = P.ID
    AND PARENT.PRWBSSEQUENCE < T.PRWBSSEQUENCE
    AND PARENT.WBS_NNBSEQ > T.PRWBSSEQUENCE
    AND PARENT.IS_OPEN_TE = 0)
    OR T.PRID IN
    (SELECT DISTINCT A1.PRTASKID
    FROM PRASSIGNMENT A1, PRTIMEENTRY TE1
    WHERE TE1.PRASSIGNMENTID = A1.PRID
    AND TE1.PRTIMESHEETID = <TimesheetId>)
    ) ) SORTABLE_DATA_SET ORDER BY PROJECT_NAME asc, PRWBSSEQUENCE asc;



    Before running the query, you should perform the required checks on GUI, e.g. -

    Project -
    Open for time-entry
    Track-mode = Clarity

    Task -
    Open for time-entry
    Any parent tasks should also be open for time-entry

    Resource -
    Open for time-entry
    Track-mode = Clarity
    Should be assigned to the task, and from the assignment perspective (Application side > Resource > Resource Profile > Allocations ::: there is a time-entry check-mark, which should be checked)


    NJ


  • 5.  RE: Timesheet - Task cannot be added into timesheet

    Posted Mar 29, 2013 10:41 AM
    Use the search and see also
    98151982
    Cannot select task in Time Sheet

    Martti K.