AnsweredAssumed Answered

Availability Rate for the Resources - how to change programatically

Question asked by JoanKelley4209671 on Apr 4, 2013
Latest reply on May 6, 2013 by another_martink
Hello,
I must change all of my resources availability from 8 hours per day to 7 hours per day.

I know I can go one by one and edit this field from an 8 to a 7 but I would like to do this programmatically. In the Resource Object it does not provide the table or field name for this data. Does anyone know which table or fields this data lives in?
Or is there another underlying way to modify availability across the board?

I opened the Base Standard Calendar and I did not see it there.
thanks,
Joan

Outcomes