I want to upgrade introscope and CEM from 9.0.5 to 9.1.5 and also want to restore the exisitng data/configuration on the new system. Our installation is currently on Linux. Is there any recommendation before upgrading the system or I can simply follow the steps given in upgrade document.

1. Uninstall existing Workstations and EPAgents.
2. Upgrade the APM database.
3. Upgrade Enterprise Managers. If needed, install additional Enterprise Managers.
4. Install new Workstations and EPAgents.
5. Upgrade agents.
6. Upgrade the CA APM extensions.
7. Upgrade TIMs.
8. Verify installations and connections.


Thanks and Regards,
Mukesh Singh