AnsweredAssumed Answered

XOG Allocations

Question asked by Lowell on May 6, 2013
Latest reply on May 7, 2013 by Dave
I am attempting to XOG Allocations to Projects, and it does not seem to output what is expected.

I am trying to input Allocation entries for resources.

<NikuDataBus xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" xsi:noNamespaceSchemaLocation="../xsd/nikuxog_project.xsd">
<Header action="write" externalSource="NIKU" objectType="project" version="13.0.1.0102"/>
<Projects>
<Project name="Ability to define PIMS IDs in a status in the SIF queue higher than Batch, lower" projectID="c20101113-0000000276">
<Resources>
<Resource availFrom="2010-11-13T08:00:00" availTo="2014-11-13T17:00:00" defaultAllocation="0.2500" resourceID="r625021">
<AllocCurve/>
<HardAllocCurve>

<segment finish="2014-11-13T17:00:00" rate="0.3300" start="2010-11-13T08:00:00"/>
<segment finish="2015-11-13T17:00:00" rate="0.4400" start="2014-11-14T08:00:00"/>
</HardAllocCurve>
<SkillAssocs/>
</Resource>
</Resources>
</Project>
</Projects>
</NikuDataBus>

I would expect to have "2 rows in the Investment Allocation entry for the resource: 1 entry for 11/14/2014 - 11/13/2015 (44%) and 1 entry for 11/13/2010 - 11/13/2014 (33%)".

The result I get is: 1 "default row" 11/13/2010 - 11/13/2014" and a "default allocation % of "25%"

What am I missing on this allocation XOG?