Timesheet ETC showing different to MSP

Question asked by matpj on May 22, 2013
Latest reply on May 22, 2013 by another_martink
Hi all,

We have a resource assigned to a task which has 3.75h this week.
When she opens her timesheet and selects the task - it shows an ETC of 2.5 hours.

Can anybody tell me why the two numbers don't tally.

We have all sorts of issues with ETCs changing in MSP/Clarity - so i'd like to try to understand the factors here.


thanks in advance,
Matt