MSP seems to use 'standard' calendar rather than the resource calendar

Question asked by matpj on Jun 4, 2013
Latest reply on Jun 4, 2013 by another_martink
Hi all,

we seem to be having a spot of bother with MSP and how it sees the daily shift.
No matter how the resource calendars were set up (7.5 hour working day) MSP kept using 8 hour days.

I looked into this and noticed one of the base calendars (set as 8 hour days) had the 'Standard' checkbox checked.


We have numerous calendars set up, so I then checked the Standard checkbox on a calendar which uses 7.5 hour days.
this seems to have corrected the issue in MSP.

However, we need it to use the resource calendars, not a single base calendar - as we have resources from different global regions working on the same projects.

Should I be doing something differently here? Is there a way of getting MSP to look at the individual resource calendars when scheduling?


thanks in advance,
Matt