Hi,
we have just moved to v12.1.1 to 12.1.3 to get a better user experience in terms of saving data back to clarity, As i understand it does the Delta processing.
But it is not saving the project back to clarity if the project is big(200 resources, 8 baselines, 500 Tasks, 2000 assignments).

Have anyone experienced the similar issue?

Thanks,
manish