Hi,
We have an extract (job) which can use Relative date for the start date and end date. Our work week is from Sunday - Saturday. But when I pass the relative date like Start Date: Start of Previous week and end date: End of previous week, it should ideally take from Last Sunday to Last Saturday but its actually taking Monday - Sunday. This is providing incorrect info in the extract data.
Any idea why is this happening? Also from where is the relative date calculated. I checked in the reports and jobs under admin under parameters, and its actually poiting to a java code.
Please let me know if you have any idea on this.
-Jerin