Suppose the timesheet approval is driven by a process wherein the respective PMs will approve the task time entry.
PM A approves for Task A (20 hrs)
PM B returns for Task B (30 hrs)

The resource adjusts the timesheet such that they delete timeentry row for Task A (20 hrs - approved by PM A), and fill 40 Hrs for Task B.

This is then submitted and is approved by PM B.

Question - What will happen to the hours that were approved by PM A ? Will it go into Pending Actuals ?