AnsweredAssumed Answered

MSP: start date on task is 'NA'

Question asked by deepud on Jul 16, 2013
Latest reply on Jul 16, 2013 by another_martink
Hi All,

I have a poject that when downloaded to msp shows 'NA' for Start date field in a task.
The task has zero actuals and etc in clarity. The start and end dates in clarity are same while %complete=0

I am using clarity ppm 13.1 and msp 2007.
Is there any setting in msp that i should change? Any ideas why this happens?

Thanks,
D