I've written some data to a cost plan set with 'yearly' period type and this seems to be working to meet the business need.

Now that I'm checking to make sure I can report on the data, I see the yearly breakout seems to be stored in BLOB columns. Since there's only one row for a project where I have 'forecast cost' and 'revenue' each broken out for 3 yearly totals; I'm assuming this has to be in a BLOB column.

Now I tried 'project: detailed planned cost' and 'investment cost plan'. I do not see any data produced by these slicing jobs.

Finally, the question: --- > Does anyone know what time slice item I would setup to get 'forecast cost' and 'revenue' from a cost plan written to flat table data so I can access for reporting?

Thanks,