Does anybody have and updated summary for all the places where inactive resources are not included when summarizing actuals and actual cost for v12.1?

Eg
Project list
Project dashboard
Team staff
Team detail
Task list
WBS list
Assignments
Cost plan
Budget
Rate matrix
Portfolio
Hierarchy financial rollup
Hierarchy effort rollup
WIP
Timeslices of all sorts
Licenses

Does setting a DOT make a difference?