real start date has changed

Question asked by RonaldoRezende-TecBan on Sep 10, 2013
Latest reply on Sep 23, 2013 by Michael Thibault
Hi!
Last week, I've setted 90% complete in an task in MS Project.
The resource assigned in this task hasn't appointed any hour in time sheet last week.
Today, I've perceived that Clarity has changed my real start date to 09/09/2013 and setted 0 hours as real work.

Why this occured? Can you explain me what's happened?