Hi All,

I need your urgent help on resource weekly etc query. I have created a query which is giving me correct result for one project but for other project data is not displaying properly. I have tried everything but couldn't get it working properly. We have one requirement where project managers need to see etc hours in MSP should be same to the query result. I tried to resliced time slices, ran time slice job, ran datamart job for resource portlet.

I also used weekly, daily and system slices, searched everywhere in the community but no success so far.

Hope someone help me..