Project Finish Date in Clarity

Question asked by nmanoha on Sep 27, 2013
Latest reply on Sep 30, 2013 by another_martink
Hi All,

I want to know how the “Project Finish Date “ in Clarity is stored.

I know that the finish date in Clarity UI is always displayed one day less ‘Finish Date - 1’ format as of the value in DB.

But currently I have two projects in question ,


Project A is having Finish Date same as in UI and DB  Finish date(UI) = ‘12/20/13’ and Finish Date(DB) = ‘20-DEC-13’.

Project B is having Finish date-1 in UI but finish Date in DB  Finish date(UI) = ‘12/31/2014’ and Finish Date(DB) = ‘01-JAN-15’.

I’m checking the Table INV_INVESTMENTS in DB for both the projects.

Any reason why this is happening?

Thanks