Question asked by RonaldoRezende-TecBan on Oct 2, 2013
In the CA Green Book "Clarity PPM Integration Best Practices for Microsoft Office Project", I've read that CA recomends to keep unmarked the MSP option "Actual costs are always calculated by Microsoft Office Project".

Whats the impact of activating this option?