Question asked by Rajani on Oct 3, 2013
Latest reply on Oct 3, 2013 by another_martink
Hello,

We have a requirement to manage resource availability (PTO) in Clarity and we are planning to xog in resource calendar info. The question here is it is possible for resources to take half day PTOs.
I checked the xog and xsd and isWorkDay is defined at the day level but not at the shift level.

Please advice on how this can be achieved. Thanks in advance.

Thank you,
Rajani.