TSV / Slice for Resource Requisitions

Question asked by AlistairMiller on Dec 10, 2013
Latest reply on Dec 15, 2013 by AlistairMiller

I'm trying to produce a portlet that will show for each Resource Requisition, the number of hours requested by month.  The OOTB portlets won't work for me, as I need to coalesce the information together with other information and present it in a specific way.

It doesn't look to me like the blob which holds this information is exploded in the same way as other time-slice values such as Allocations (at least, I couldn't see any likely candidates in PRJ_BLB_SLICEREQUESTS).

Has anyone done anything like this previously, and if so, where should I be looking? I'm on v13.1, Clarity On Demand. DB is Oracle.

Many thanks in advance!