Hi All,

When assigning any resources after 01/1/2014, the resources’ cost is automatically set to zero for one of my projects. One thing I noticed is even though the project end date is 12/31/2014, the base line end date is 12/31/2013. Is it related to this? If so how can I change the base line end date.

Thanks in advance,

Sreelesh