Populating timesheet with proposed ETC

Question asked by clarity_user_kf on Jan 23, 2014
Latest reply on Jan 24, 2014 by suhail_sayed

Hello together, I have got a question concerning populating timesheet and changing proposed ETC. When changing proposed ETC to 0 (and "original" ETC ist not 0) the task is no longer populated (assignment dates and actuals do not matter). When changing proposed ETC to e.g. 10 and "original" ETC is 0 the task is only populated if there are no actuals on the task (here also assignment dates do not matter). Can somebody explain why tasks are not populated if proposed ETC > 0, "original" ETC = 0 and actuals>0? Than you for you help!