Hi,
I have got a question concerning BAC calculation.
The formula says "BAC = ((Actuals + Remaining Work) x Billing Rate) taken at time of baseline". Unfortunately I don't know exactly how to handle billing rate. I added "billing rate" to OWB view and changed the value but BAC was not changing. I also changed the rate value within the clarity matrix (where I can also enter standard cost and actual cost) but this had also no effect on BAC. Can somebody explain to me where I can set up the billing rate for calculating the BAC?

Thank you for your help!