ETC vs duration - reschedule based on ETC

Question asked by Vit_Posel on Feb 17, 2014
Latest reply on Feb 26, 2014 by Vit_Posel

Have task with duration 1 day

ETC 20 hours with resource availability 8 hours

Is there any way how to reschedule duration of the task based on ETC - for this example to 3 days like its rescheduled in MSP?

Thanks in advance

 

Vit