AnsweredAssumed Answered

Plan Cost

Question asked by Nei_Lojas_Renner_SA on Mar 5, 2014
Latest reply on Mar 7, 2014 by Connie_Fu

Hi community.

I have created 10 tasks in WBS to aggregate project´s expenses. This tasks has resources assigned (financial enabled), and I expect creating a Plan cost just with this 10 tasks (all other task has resources FINANCIAL DISABLED), but when I use  FINALCIAL PLANS > ACTIONS -> New From Task Assignments a lot of tasks with ACTUALS are created on plan.

Is there a way to select tasks to export to plan?

Regards,

Nei Villas Boas.

 