AnsweredAssumed Answered

setting duration status on processes in PAM 4.2

Question asked by samuel.leibowitz on Mar 22, 2014
Latest reply on Mar 18, 2016 by Scott_Owens

Hi all,

Is there some sort of restriction on the use of the duration status attributes (Expected Duration, Warning Threshold) on sub-processes?  I've noticed that in  a demo I set up for some colleagues, I have a test process with an expected duration set.  When I start that process by itself, I see the duration status appear in the process watch; when I call it from another process using the "Start Process" operator, it comes up blank.  Is that normal behavior?

Thanks in advance,

Sam

Outcomes