No change in ETC value after adjusting the posted timesheet

Question asked by Dhivya_1 on Mar 27, 2014
Latest reply on Mar 29, 2014 by another_martink

Adjusted a posted timesheet for a resource with a task, corresponding adjusted hrs is not reflecting in ETC (increment/decrement based on the adjustment).

 

Eg : Posted timesheet - 40 hrs and ETC -100.. Adjusted the timesheet to 30hrs.

Actuals are reflecting exactly as 30 hrs after adjustment,except the ETC (ETC still shows as 100 instead 110 hrs).

 