AnsweredAssumed Answered

Changing Actuals Thru Date

Question asked by NickiB on May 15, 2014
Latest reply on May 16, 2014 by Debz_MacArthur

Hi,

Is it possible to change the actuals thru date?

A timesheet was posted for July instead of April, the timesheet has been adjusted so the actuals have been removed, but the actuals thru date is still July. So all tasks are now being re-scheduled after July for this resource.

Can anyone suggest how to fix this?

Many Thanks In Advance! :)