Clarity

  • 1.  MSP 2013 base line issues with Clarity 13.3

    Posted May 19, 2014 12:00 PM

    All

    We have installed Clarity 13.3.0.286 03 11

    I have MSP 2013 installed. I can take a project from Clarity to MSP 2013 that IS NOT baselined. It pulls up fine and I can upload it  back to CLarity fine.


    When I attempt to pull a project from Clarity to MSP 2013 that is BASELINED, it starts to pull dowm the tasks etc. Then the popup states" down loading baseline" it just hangs and a pop up comes up "Schedlink MFC Application has stoped working". Tells me to close program.

     

    Is there a fix for MSP 2013 vs. CLarity version 13.3.0.286 03 11 regarding baselined projects??

     

    MIke

     



  • 2.  RE: MSP 2013 base line issues with Clarity 13.3

    Posted May 19, 2014 03:01 PM

    We went from 12.1.1 to 13.3.3 and from MSP 2007 to MSP 2013.

     

    The fix here is to delete all the projects 5xxxxxxx numbers from:

    Delete from PRdocument where PRrecordID=5027169

    This appears to work. I am going to test more to verify.

    Mike



  • 3.  RE: MSP 2013 base line issues with Clarity 13.3

    Posted May 20, 2014 01:24 PM

    How did you learn about sthe fix?

     

    Martti k.



  • 4.  RE: MSP 2013 base line issues with Clarity 13.3

    Posted May 20, 2014 01:32 PM

    We had a webex with a CA tech and this tech came up with the fix.

     

    Mike



  • 5.  Re: MSP 2013 base line issues with Clarity 13.3

    Posted Dec 29, 2014 05:40 AM

    "  The fix here is to delete all the projects 5xxxxxxx numbers from:  Delete from PRdocument where PRrecordID=5027169

      This appears to work. I am going to test more to verify

    "

     

    Were you able to resolve your issue ?

     

    If you can provide some more info, would be great

     

    NJ