ETC Value issue after time sheet adjustment

Question asked by Ashwin.soni on May 28, 2014

Hi

When resource submitted time get posted in Clarity, the current ETC gets reduced. However when resource adjust the same timecard and make the Posted actual to ZERO on project, then ETC value on task in Clarity/OWB should get added back. But this is not happening in Clarity. We are using V12 of Clarity. Please help. Thanks in advance.