MS Project question

Question asked by Juan_Ortega on Dec 8, 2010
Latest reply on Dec 14, 2010 by Michael
MS Project has three task types: Fixed Duration, Fixed Unit, and Fixed Work.

When Fixed Unit or Fixed Work is set to YES in MS Project, the Fixed Duration field would be set/mapped to NO, if the project is opened in Clarity.

Why does this occur and what does the user lose if the Fixed Duration is set to NO?