Resource calenders

Question asked by els.langenus on Feb 11, 2011
Latest reply on Feb 18, 2011 by another_martink
We want to work with the resource calenders.

But there is a problem when you change the regime of a resource for example from working 5 days a week to 4 days a week.
If I click on the day for example Tuesday, I can make this a non-working day. But then this changes the whole resource calander. So if this resource only works 4 days a week for a period of for example a month, you have to change this manually (by clicking on each tuesday of that period/

Is there a sollution or a workaround for this?