urgent help needed regarding resource

Discussion created by SonalVaidya on Mar 18, 2011
Hi All,

I need some urgent help regarding resource finder functionality in Clarty , what I have done so far is -

1.
In resource calendar I made few days as a non-working days ( for example 12/12/2011 and 14/12/2011)
2.
Executed time slices job manually to get the slices stored (verify “dailyresourceallocation” curve has values till 2012).
3.
Filter resources finder portlet on the basic of availability criteria ( i.e. . 12/12/2011 to 16/12/2011 , 5 days)
4.
When I click on the filer resources is still showing 100% available.
5.
Try to book soft book resource in a project and checked “include soft-booked resource” but still 100% availability.

Is there anything I am missing ? Are there any specific step to achieve this result?

Any help would be highly appreciated.