We have only dealt with US sites and projects up to now. We want to add projects for a facility in Scotland. To make things easier, we plan to show their costs in US Dollars so we don't have to mess with Multi-Currency. We use a flat rate for all labor resources. Scotland will have different rates than US. Do I build a cost matrix just for Scotland or do I add lines to our current Rate Matrix for the Scotland resources?

I've tried it both ways. When I created a separate rate matrix, I tied the matrix to the Scotland location. I then created a test project and pointed to the scotland matrix on the financial properties page. I ran the rate matrix extraction job, and when I tried to create a cost plan, I got a message stating that one or more of my resources had no rate.

When that didn't work as anticipated, I scrapped the Scotland rate matrix, and added lines to the current rate matrix. I indicated that the rate was to be used for the Scotland location and Scotland Resource. When I created the cost plan, it ignored the Scotland rate and used the US rate.

What the heck am I doing wrong??