Hi

Based on the below thread, I've a few questions -

2301188

1. Can we somehow change the access rights for Project / Resource Manager (Auto) ? If yes ? How / where ? (I knw that this wld be unsupported)

2. In case we go for a db trigger, then consider the below scenario -

Resource A has resource manager B. Now, if we change are able to somehow remove the resource manager rights of B on A, and give equivalent rights, except for Resource - Edit, then, should we be able to maintain B in the Resource Manager field for A ? Is there a way this can be achieved ?

Regards
NJ